FAIR Commissioning Phase A.1.1.01) -- Commission Final Meters of Preceding Transfer Line

Specifics

For details of the commissioning of the lcoal injector see topic "Commissioning of the Local Injector"

Scope of Phase

The following sections shall be defined as "the final meters of the injection section":
  • Part of beam line GHTY between gate valve GHTYVV1T (exclusive) and gate valve GHTYVV2T (inclusive). In detail the following components and technical systems are involved:
    • Vaccum:
    • Beam optics + related power converters
      • vertical steerer GHTYKV3
      • quadrupole doublet lens GHTYQD41, GHTYQD42
    • Beam diagnostics
      • diagnostic chamber GHTYDK3 with
        • Cromox fluorescent screen GHTYDF3 + pneumatic actuator GHTYDF3_P
    • Control System
      • Timing System
      • End user applications + related controls stack

For Details see CryringWiki page " GHTY Transferline Details"

Description

Goal of this commissioning phase is to thread the beam from ESR up to detection box GHTYDK3 and check operation-readyness of all active elements in this section.
  • Vacuum < 10<sup>-9</sup> mbar (10<sup>-11</sup> mbar for stored beam operation)
  • Beam can be manipulated according to expectations with GHTYKV3, GHTYQD4x
  • Beam spot is visible on GHTYDF3 with spot size of XXX mm

Entry Conditions

clear definition of handover specs: definition of must-have systems,
op. procedures (e.g. machine patrol)

Entry Condition
Special Entry Conditions
YR GS GE 1S CR HR
E.A.1.1.01.1 Vacuum components passed dry run
E.A.1.1.01.2 Beam optical elements passed dry run
.01 GHTYKV3 passed dry run
.02 GHTYQD41 passed dry run
.03 GHTYQD42 passed dry run
E.A.1.1.01.3 Beam diagnostics passed dry run
.01 GHTYDF3 passed dry run
.02 GHTYDF3_P passed dry run
E.A.x.3 entry condition 3
.01

Notes on Entry Conditions

  1. Applications
  2. Beam Instrumentation
    • Wire Grids
      • item assumed to be commissioned before
      • item assumed to be commissioned before
    • DC Current Transformers
      • item assumed to be commissioned before
    • BPMs
      • item assumed to be commissioned before

  3. Machine Protection System
    • Interlock System
    • Fast Beam Abort System

Machine Setup

Definition of optics, beam parameters, machine protection equipment that needs to be in placeMP equipment in place
  • CRYRING
    • Machine Optics: ion optics -- reference to name in LSA
    • Beam Parameter: tbd.
    • Global Beam Pattern: tbd.
    • Machine Protection: not-applicable

Procedure

Step Activity Who Priority Special specific Procedures
YR GS GE 1S CR HR
A.x.1 result 1 (as described above)
.01
.02
.03
A.x.2 result 2 (as described above)
.01
A.x.3 result 3 (as described above)
.01
(N.B. priority definition 1: must, 2: optional, 3: nice to have, if time available -- 2&3: optional items, e.g. for night-time shift or if commissioning delayed by another item)

To be considered: required time - minimum (rough estimate, smallest time quantity 1h, otherwise given in terms of 8h shifts) required time - contingency (rough estimate, subjective at this time but should not reflect worst-case)

Details of activities

N.B. detailed 'cookbook': check list of individual steps (settings, gains, …):

Step A.x.1 result 1 (as described above)

  1. step 1 (pictures, links, and references possible)
    • sub-step 1.1
    • sub-step 1.2
    • sub-step 1.3
  2. step 2
  3. step 3

Step A.x.2 result 2 (as described above)

  1. step 1

Step A.x.2 result 2 (as described above)

  1. step 1

Problems

List of possible problems and first-order remedies:

  • short problem description #1
  • short problem description #2

Exit conditions

clear definition of handover specs

List of systems to be considered “operational” afterwards

Exit Condition
Priority
O.A.x.1 exit condition 1
O.A.x.2 exit condition 2
.01 sub-system 1
.02 sub-system 2
.03 sub-system 3
O.A.x.3 exit condition 3
.01

Notes on Exit Conditions

  1. Applications
  2. Beam Instrumentation
    • Wire Grids
      • item assumed to be operational/working afterwards
      • item assumed to be operational/working afterwards
    • DC Current Transformers
      • item assumed to be operational/working afterwards
    • BPMs
      • item assumed to be operational/working afterwards
  3. Machine Protection System
    • Interlock System
    • Fast Beam Abort System

Open Questions & Action Items

things that are not yet discussed, or integrated into the procedure

References

  1. <reference #1 title>, author, date, source link
  2. <reference #2 title>, author, date, source link

Acronyms

Acronyms

Abbreviation alt. English German
BPC BeamProductionChain Beam Production Chain
BPM Beam Position Monitor Strahllage Monitor, Positions Sonde
COD Closed Orbit Dipole (Steerer) Strahllage Korrektur Magnet
DCCT Direct Current (DC) - Curent Transformer

Copyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding Foswiki Send feedback | Imprint | Privacy Policy (in German)
This website is using cookies. More info. That's Fine