FAIR Commissioning Phase A0.1) -- Commissioning of the Local Injector
Scope of This Phase
The following parts and devices of the CRYRING@ERS beamline shall be defined as the "Local Injector":
All equipment upstream of the vacuum valve YRT1VV4T including dipole magnet YRT1MH2 (a.k.a. "merging magnet", "35 degree magnet". In detail the following components and technical systems shall be considered:
- Vacuum
- Passive elements of the beamline (vacuum tubes and - chambers)
- Locally operated valves YRT1VV2L, YRT1VV3L, YRT1VV4L, YRT1VV5L
- Remotely operated valves YRT1VV1T, YRT1VV2T, YRT1VV3T, YRT1VV4T
- Turbo molecular pumps YRT1VP1T1, YRT1VP1T2, YRT1VP2T, YRT1VP3T, YRT1VP4T, YRT1VP5T
- Ion getter pumps YRT1VP4I, YRT1VP6I, YRT1VP7I
- Vavcuum gauges YRT1VM1P, YRT1VM1T1, YRT1VM2P, YRT1VM1T2, YRT1VM3P, YRT1VM4P, YRT1VM4T, YRT1VM6P, YRT1VM6T,
- Ion source devices and related power supplies
- Beam optics and related power supplies
- Linear accelerator RFQ YRT1BR1 and related power supplies
- Beam diagnostics
- Control system
- Timing System (required for operation of RFQ + beam diagnostics)
- end user application and related software / hardware stack
Description
In this phase the local injector (a.k.a. "linear accelerator", "offline ion source")
Short bullet point list description of should be achieved
- result 1 (→ step 1)
- result 2 (→ step 2)
- result 3 (→ step 3)
Entry Conditions
clear definition of handover specs:
definition of must-have systems,
op. procedures (e.g. machine patrol)
| Entry Condition
| Special Entry Conditions |
YR | GS | GE | 1S | CR | HR |
E.A.x.1 | entry condition 1 | | | | | | |
E.A.x.2 | entry condition 2 | | | | | | |
.01 | sub-system 1 | | | | | | |
.02 | sub-system 2 | | | | | | |
.03 | sub-system 3 | | | | | | |
E.A.x.3 | entry condition 3 | | | | | | |
.01 | | | | | | | |
Notes on Entry Conditions
- Applications
- Beam Instrumentation
- Wire Grids
- item assumed to be commissioned before
- item assumed to be commissioned before
- DC Current Transformers
- item assumed to be commissioned before
- BPMs
- item assumed to be commissioned before
- Machine Protection System
- Interlock System
- Fast Beam Abort System
Machine Setup
Definition of optics, beam parameters, machine protection equipment that needs to be in placeMP equipment in place
- CRYRING
- Machine Optics: ion optics -- reference to name in LSA
- Beam Parameter: tbd.
- Global Beam Pattern: tbd.
- Machine Protection: not-applicable
- SIS18
- Machine Optics: ion optics -- reference to name in LSA
- Beam Parameter: tbd.
- Global Beam Pattern: tbd.
- Machine Protection: tbd.
- ESR
- Machine Optics: ion optics -- reference to name in LSA
- Beam Parameter: tbd.
- Global Beam Pattern: tbd.
- Machine Protection: not-applicable
- SIS100
- Machine Optics: ion optics -- reference to name in LSA
- Beam Parameter: tbd.
- Global Beam Pattern: tbd.
- Machine Protection: tbd.
- CR
- Machine Optics: ion optics -- reference to name in LSA
- Beam Parameter: tbd.
- Global Beam Pattern: tbd.
- Machine Protection: tbd.
- HESR
- Machine Optics: ion optics -- reference to name in LSA
- Beam Parameter: tbd.
- Global Beam Pattern: tbd.
- Machine Protection: not-applicable
Procedure
Step | Activity | Who | Priority | Special specific Procedures |
YR | GS | GE | 1S | CR | HR |
A.x.1 | result 1 (as described above) | | | | | | | | |
.01 | | | | | | | | | |
.02 | | | | | | | | | |
.03 | | | | | | | | | |
A.x.2 | result 2 (as described above) | | | | | | | | |
.01 | | | | | | | | | |
A.x.3 | result 3 (as described above) | | | | | | | | |
.01 | | | | | | | | | |
(N.B. priority definition 1: must, 2: optional, 3: nice to have, if time available -- 2&3: optional items, e.g. for night-time shift or if commissioning delayed by another item)
To be considered: required time - minimum (rough estimate, smallest time quantity 1h, otherwise given in terms of 8h shifts)
required time - contingency (rough estimate, subjective at this time but should not reflect worst-case)
Details of activities
N.B. detailed 'cookbook': check list of individual steps (settings, gains, …):
Step A.x.1 result 1 (as described above)
- step 1 (pictures, links, and references possible)
- sub-step 1.1
- sub-step 1.2
- sub-step 1.3
- step 2
- step 3
Step A.x.2 result 2 (as described above)
- step 1
Step A.x.2 result 2 (as described above)
- step 1
Problems
List of possible problems and first-order remedies:
- short problem description #1
- short problem description #2
Exit conditions
clear definition of handover specs
List of systems to be considered “operational” afterwards
| Exit Condition
| Priority |
O.A.x.1 | exit condition 1 | |
O.A.x.2 | exit condition 2 | |
.01 | sub-system 1 | |
.02 | sub-system 2 | |
.03 | sub-system 3 | |
O.A.x.3 | exit condition 3 | |
.01 | | |
Notes on Exit Conditions
- Applications
- Beam Instrumentation
- Wire Grids
- item assumed to be operational/working afterwards
- item assumed to be operational/working afterwards
- DC Current Transformers
- item assumed to be operational/working afterwards
- BPMs
- item assumed to be operational/working afterwards
- Machine Protection System
- Interlock System
- Fast Beam Abort System
Open Questions & Action Items
things that are not yet discussed, or integrated into the procedure
References
- <reference #1 title>, author, date, source link
- <reference #2 title>, author, date, source link
Acronyms
Acronyms
Abbreviation | alt. | English | German |
BPC | BeamProductionChain | Beam Production Chain | |
BPM | | Beam Position Monitor | Strahllage Monitor, Positions Sonde |
COD | | Closed Orbit Dipole (Steerer) | Strahllage Korrektur Magnet |
DCCT | | Direct Current (DC) - Curent Transformer | |