This web coordinates the hardware (re-)commissioning (HWC) of the existing and future FAIR accelerator facility. The term 'hardware commissioning' covers the following two aspects:
Initial hardware acceptance tests
- Checks conformity with contractual design targets
- Done once, or after major upgrade or modifications
- mainly done by system responsible/experts
- coordinated by existing project structure and machine project leaders (i.e. not FC2WG)
- FATs - Factory-Acceptance-Tests
- SATs - Site-Acceptance-Tests
'Dry-Runs' & 'Machine Checkout'
- main aim:
- Checks conformity of system's controls integration and readiness for Commissioning with Beam
- check as much control/system functionality without beam as possible
- Machine is put into a state assuming that beam could be injected into the ring/segment
- unavailable devices/systems are at first ignored, noted down, and followed-up at a defined later stage
A note on terminology:
- Dry-runs: a rehearsal of the accelerator performance/function, starting typically six month before the targeted real Commissioning with Beam
- needs to (partially) repeated after shut-down or longer technical stop with substantial modifications (e.g. re-cabling, opening of cryogenic, …)
- initial frequency: 1-2 days every month
- frequency increased depending on the outcome of the initial dry-run tests
- Machine Checkout: intense accelerator performance tests (e.g. machine patrols, magnet/PC heat runs, etc.), starting typically two weeks before the targeted Commissioning with Beam)
- needs to repeated after every shut-down or longer technical stop
- repeated also on the long-term during routine operation of existing accelerators (already existing procedures/usus for existing machines)